To construct a cassava starch processing project, many preparatory works need to be finished, such as conduct project feasibility analysis, prepare funds, raw materials and plant land, purchase cassava starch processing machine, etc. And according to Jinrui’s 10+ years cassava starch processing project installation experience, it takes at least half of a year to finish the construction of the entire cassava starch processing project.
This article will show you the detailed timeline, including preparation cycle, machine manufacture cycle, delivery cycle and installation cycle.
Cassava starch processing plant project in Indonesia
1.Fundamental preparatory work cycle: uncontrollable
The preparatory works needed to finish in the fundamental preparatory work cycle include conducting project feasibility analysis, raise funds, collect cassava raw materials, select land site and prepare plant land, purchase cassava starch processing machine.The real timeline in this cycle subject to the actual execution situation of investors.
2.Cassava starch processing machine manufacture cycle: about 2-3 months
The machine manufacture cycle is influenced by two factors: one is the processing capacity of cassava starch processing machine, and the other is company's order arrangement. And it takes about 2-3 months to finish the machine manufacture.
Cassava starch processing equipment
3.Cassava starch processing machine delivery cycle: about 2 months
Commonly speaking, the machine delivery cycle is influenced by transportation distance and transportation company situation, it takes less time to delivery machine by direct shipment then transshipment. And the detailed cycle is about 2 months.
Cassava starch processing machine delivery photo
4. Cassava starch processing machine installation cycle: about 2-3 months
The works needed to executed in this cycle consist of machine installation, machine commissioning, trial run, workers training, etc. The machine installation cycle mainly varies from the machine processing capacity, worker cooperation, work efficiency, cassava starch processing plant construction and installation tools completeness, etc. In general, it takes about 2-3months to finish the installation cycle.
Cassava starch processing machine installation photo
Henan Jinrui Company has helped clients from more than 30 countries and regions to install the cassava starch processing project. According to clients’ feedback, they feel satisfied with our high starch extraction rate cassava starch processing machine and complete after-sales service. If you have interests in investing cassava starch processing project, please call us for machine customized service and detailed processing solutions.